The objective of the project is to improve energy efficiency of selected coal-fired power generation units through renovation and modernization (R&M) and improved operations and maintenance (O&M), and a significant co-benefit of the project is the reduction of greenhouse gas emissions per kilowatt hour of electricity generated.

Project Details

GEF Project ID
2946
Country
India
Implementing Agencies
The World Bank
Approval FY
2009
Status
Completed
Region
Asia
Executing Agencies
World Bank
GEF Period
GEF - 3
Project Type
Full-size Project
Focal Areas
Funding Source
GEF Trust Fund

Financials

USD
Co-financing Total
258,000,000
GEF Project Grant
45,400,000
GEF Agency Fees
4,086,000

Timeline

Received by GEF
12 Oct 2005
Concept Approved
01 Aug 2006
Project Approved for Implementation
18 May 2009
Project Closed
23 Oct 2018