Geothermal Resource Development in Saint Lucia

Project Summary

The development objective of the project is to provide support for GoSL to make an informed decision regarding geothermal exploration and development in Saint Lucia by undertaking key upstream preparatory activities.

Project Details

GEF Project ID
5812
Project Type
Medium-size Project
Status
Project Approved
Country
St. Lucia
Region
Focal Areas
Funding Source
GEF Trust Fund
Implementing Agencies
The World Bank
Executing Agencies
Ministry of Sustainable Development, Energy, Science and Technology, Ministry of Finance and Economic Development
GEF Period:
GEF - 5
Approval Fiscal Year:
2014

Project Documents

Financials

Project Preparation Grant Amount
0 USD
GEF Project Grant
1,000,000 USD
Co-financing Total
32,575,000 USD
GEF Agency Fees
95,000 USD
Total Cost 33,575,000.00 USD

Project Timeline

Received by GEF
25 Apr 2014
Concept Approved
12 May 2014
Project Approved for Implementation
20 Nov 2014
Project closed