The general objective of the project is to develop new guidance document, update existing guidance documents, validate them, and make them available for assisting countries in the preparation and updating their NIPs under the Stockholm Convention, considering the new obligation parties have to comply with after the listing of 9 new POPs.

Project Details

GEF Project ID
4410
Country
Global
Implementing Agencies
United Nations Industrial Development Organization
Approval FY
2011
Status
Completed
Region
Global
Executing Agencies
Secretariat of the Stockholm Convention, UNITAR
GEF Period
GEF - 5
Project Type
Medium-size Project
Focal Areas
Funding Source
GEF Trust Fund

Financials

USD
Co-financing Total
1,022,700
GEF Project Grant
719,000
GEF Agency Fees
71,900

Timeline

Received by GEF
03 Nov 2010
Concept Approved
09 Feb 2011
Project Approved for Implementation
08 Feb 2011
Project Closed
11 Dec 2015