The overall objective of the proposed Enabling Activities (EA) is to review and update the National Implementation Plan (NIP), and have it endorsed and submitted by the government to the Stockholm Convention Conference of Parties (COP). Participating stakeholders will be able to manage the additional POPs with newly developed technical skills, expertise and awareness.

Project Details

GEF Project ID
5469
Country
Senegal
Implementing Agencies
United Nations Industrial Development Organization
Approval FY
2013
Status
Completed
Region
Africa
Executing Agencies
Ministry of Environment and Sustainable Development
GEF Period
GEF - 5
Project Type
Enabling Activity
Focal Areas
Funding Source
GEF Trust Fund

Financials

USD
Co-financing Total
180,000
GEF Project Grant
170,000
GEF Agency Fees
16,150

Timeline

Received by GEF
27 Jun 2013
Concept Approved
10 Jul 2013
Project Approved for Implementation
09 Jul 2013
Project Closed
14 Jul 2017