To Introduce an Integrated Energy and Ecosystems-Based Approach to Grid/Isolated-Grid-Based Mini/Small Hydro-Electricity Generation in Sao Tome and Principe.

Project Details

GEF Project ID
5334
Country
Sao Tome and Principe
Implementing Agencies
United Nations Development Programme
Approval FY
2015
Status
Project Approved
Region
Small Islands Developing States
Executing Agencies
Ministry of Energy and Natural
Resources (MENR), Empresa da
Agua e Electricidade (EMAE – water
and electricity company), Central
Bank of Sao Tome and Principe
GEF Period
GEF - 5
Project Type
Full-size Project
Funding Source
GEF Trust Fund

Financials

USD
Co-financing Total
20,705,704
GEF Project Grant
5,274,544
GEF Agency Fees
501,081

Timeline

Received by GEF
13 Mar 2013
Concept Approved
20 Jun 2013
Project Approved for Implementation
08 Jun 2015