To demonstrate PV’s effectiveness in addressing distribution system capacity issues, a 1 MW distributed generation PV power plant is proposed to be built and integrated into the 80 MW distribution network of the Cagayan de Oro Power & Light Company (CEPALCO), a private utility operation on the island of Mindanao in the Philippines. The PV system will be operated in conjunction with an existing 7 MW hydroelectric plant with dynamic load control, thereby enabling the joint PV/hydro resource to reduce both distribution level and system level demand, effectively providing “firm” generating capacity. The PV plant will also assist in postponing the need for additional substation installations in the CEPALCO distribution system for a period of up to three years. The project will thus reduce the need of CEPALCO to purchase additional quantities of thermal plant-based power, thereby reducing its emissions of greenhouse gases. However, more importantly, it is expected that this plant will provide the first, full-scale demonstration of the environmental and, ultimately, also economic benefits of the conjunctive use of hydro and PV-based power, as well as the first significant use of grid-connected PV in a developing country. If, as is expected, the large-scale introduction of this technology helps in substantially reducing PV systems’ costs, widespread applications worldwide are likely to result.

Project Details

GEF Project ID
652
Country
Philippines
Implementing Agencies
The World Bank
International Finance Corporation
Approval FY
2000
Status
Completed
Region
Asia
Executing Agencies
IFC
GEF Period
GEF - 2
Project Type
Full-size Project
Focal Areas
Funding Source
GEF Trust Fund

Financials

USD
Co-financing Total
1,775,000
GEF Project Grant
4,000,000

Timeline

Concept Approved
07 May 1999
Project Approved for Implementation
05 Sep 2000
Project Closed
20 May 2005